<?xml version="1.0" encoding="UTF-8"?>
<article xmlns:xlink="http://www.w3.org/1999/xlink" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="JATS-archive-oasis-article1-4.xsd" article-type="research-article" dtd-version="1.4" xml:lang="ru">
  <front>
    <journal-meta>
      <journal-title-group>
        <journal-title>Журнал Современные наукоемкие технологии</journal-title>
      </journal-title-group>
      <issn>1812-7320</issn>
      <publisher>
        <publisher-name>Общество с ограниченной ответственностью &amp;quot;Издательский Дом &amp;quot;Академия Естествознания&amp;quot;</publisher-name>
      </publisher>
    </journal-meta>
    <article-meta>
      <article-id pub-id-type="publisher-id">ART-36662</article-id>
      <title-group>
        <article-title>ГИПЕРВЕКТОРНОЕ РАНЖИРОВАНИЕ В МУЛЬТИПРОЕКТНОМ ПЛАНИРОВАНИИ</article-title>
      </title-group>
      <contrib-group>
        <contrib contrib-type="author">
          <name-alternatives>
            <name xml:lang="ru">
              <surname>Клеванский</surname>
              <given-names>Н.Н.</given-names>
            </name>
          </name-alternatives>
          <name-alternatives>
            <name xml:lang="en">
              <surname>Klevanskiy</surname>
              <given-names>N.N.</given-names>
            </name>
          </name-alternatives>
          <email>nklevansky@yandex.ru</email>
          <xref ref-type="aff" rid="aff1"/>
        </contrib>
        <contrib contrib-type="author">
          <name-alternatives>
            <name xml:lang="ru">
              <surname>Ткачев</surname>
              <given-names>С.И.</given-names>
            </name>
          </name-alternatives>
          <name-alternatives>
            <name xml:lang="en">
              <surname>Tkachev</surname>
              <given-names>S.I.</given-names>
            </name>
          </name-alternatives>
          <email>nklevansky@yandex.ru</email>
          <xref ref-type="aff" rid="aff1"/>
        </contrib>
        <contrib contrib-type="author">
          <name-alternatives>
            <name xml:lang="ru">
              <surname>Красников</surname>
              <given-names>А.А.</given-names>
            </name>
          </name-alternatives>
          <name-alternatives>
            <name xml:lang="en">
              <surname>Krasnikov</surname>
              <given-names>A.A.</given-names>
            </name>
          </name-alternatives>
          <email>nklevansky@yandex.ru</email>
          <xref ref-type="aff" rid="aff1"/>
        </contrib>
      </contrib-group>
      <aff id="aff1">
        <institution xml:lang="ru">ФГБОУ ВО «Саратовский государственный аграрный университет имени Н.И. Вавилова»</institution>
        <institution xml:lang="en">Saratov state agrarian university named after N.I. Vavilov</institution>
      </aff>
      <pub-date date-type="pub" iso-8601-date="2017-05-06">
        <day>06</day>
        <month>05</month>
        <year>2017</year>
      </pub-date>
      <issue>5</issue>
      <fpage>30</fpage>
      <lpage>34</lpage>
      <permissions>
        <license xlink:href="https://creativecommons.org/licenses/by/4.0/">
          <license-p>This is an open-access article distributed under the terms of the CC BY 4.0 license.</license-p>
        </license>
      </permissions>
      <self-uri content-type="url" hreflang="ru">https://top-technologies.ru/article/view?id=36662</self-uri>
      <abstract xml:lang="ru" lang-variant="original" lang-source="author">
        <p>Представлены методы решения второй задачи мультипроектного планирования – формирования календарных графиков. Две схемы формирования расписания реализованы в среде СУБД и включают формирование начального календарного графика по первой схеме и его последующую оптимизацию с помощью второй схемы. Каждая схема циклична, так как содержит две «жадные» эвристики в виде правил приоритетов. В каждом цикле результат работы первого правила схемы используется вторым правилом. В каждом правиле осуществляется выбор наиболее приемлемого критерия загруженности или равномерности с принятием некоторых решений. В операциях выбора используются различные методы ранжирования теории принятия решений. В формировании календарных графиков использованы «жадная» идеология и концепции равномерности и загруженности. Рассмотрены численные результаты применения гипервекторного ранжирования критериев загруженности проектов в мультипроектном планировании.</p>
      </abstract>
      <abstract xml:lang="en" lang-variant="translation" lang-source="translator">
        <p>This paper is demonstrate how resource-constrained multi-project scheduling problems can be solved efficiently by two schedule generation schemes. The first, in the multi-project scheduling problem, multiple projects, each having a number of activities, must be scheduled in an initial solution. The second, in the multi-project scheduling problem, the initial solution must be optimized. A set of local and global resources are available for carrying out the activities of the projects. The basic criteria for priority rules are demanded – criterion of activity/project workload and criterion of resource equability. The solutions obtained by the first schedule generation scheme with the best resource allocation rule are used as a baseline to compare those obtained by the latter. Each schedule generation scheme consists of two priority rules – heuristic solution-finding procedures based on greedy ideology. The priority rules use multi-criteria ranking of decision support theory. The algorithm introduces the concept of an adjustable resource allocation factor which can be used to produce schedules. A numerical example of hyper-vector ranking for project workload criteria in multi-project scheduling is given.</p>
      </abstract>
      <kwd-group xml:lang="ru">
        <kwd>мультипроектное планирование</kwd>
        <kwd>заявка</kwd>
        <kwd>действие</kwd>
        <kwd>распределение ресурсов</kwd>
        <kwd>правила приоритетов</kwd>
        <kwd>схема формирования расписания</kwd>
        <kwd>многокритериальное ранжирование</kwd>
        <kwd>гипервекторное ранжирование</kwd>
      </kwd-group>
      <kwd-group xml:lang="en">
        <kwd>multi-project scheduling</kwd>
        <kwd>demand</kwd>
        <kwd>activity</kwd>
        <kwd>resource allocation</kwd>
        <kwd>priority rules</kwd>
        <kwd>schedule generation scheme</kwd>
        <kwd>multi-criteria ranking</kwd>
        <kwd>hyper-vector ranking</kwd>
      </kwd-group>
    </article-meta>
  </front>
  <back>
    <ref-list>
      <ref>
        <note>
          <p>1. Гончаров Е.Н. Стохастический жадный алгоритм для задачи календарного планирования с ограниченными ресурсами // Дискретный анализ и исследование операций. – 2014. – Т. 21, № 3. – С. 11–24.</p>
        </note>
      </ref>
      <ref>
        <note>
          <p>2. Клеванский Н.Н., Красников А.А. Формирование календарных графиков мультипроектного планирования // Образовательные ресурсы и технологии. – 2015. – № 3(11). – С. 39–60.</p>
        </note>
      </ref>
      <ref>
        <note>
          <p>3. Клеванский Н.Н., Красников А.А. Алгоритмы формирования расписаний для сетевых структур заявок/работ // Фундаментальные исследования. – 2016. – № 4–3. – С. 495–500.</p>
        </note>
      </ref>
      <ref>
        <note>
          <p>4. Сафронов В.В. Основы системного анализа: методы многовекторной оптимизации и многовекторного ранжирования: монография. – Саратов: Научная книга, 2009. – 329 с.</p>
        </note>
      </ref>
      <ref>
        <note>
          <p>5. Browning T.R., Yassine A.A. Resource-Constrained Multi-Project Scheduling: Priority Rule Performance Revisited // International Journal of Production Economics. – 2010. – № 126 (2). – P. 212–228.</p>
        </note>
      </ref>
      <ref>
        <note>
          <p>6. Chakrabortty R.K., Sarker R.A., Essam D.L. Resource Constrained Multi-project Scheduling: A Priority Rule Based Evolutionary Local Search Approach. In: Leu G., Singh H., Elsayed S. (eds) Intelligent and Evolutionary Systems. Proceedings in Adaptation, Learning and Optimization. – Springer, Cham. – 2017. – Vol 8. – P. 75–86.</p>
        </note>
      </ref>
      <ref>
        <note>
          <p>7. Dalfard V.M., Ranjbar V. Multi-Projects Scheduling with Resource Constraints &amp; Priority Rules by the Use of Simulated Annealing Algorithm // Tehnicki vjesnik. – 2012. – № 19(3). – Р. 493–499.</p>
        </note>
      </ref>
      <ref>
        <note>
          <p>8. Kolish R., Sprecher A. PSPLIB – A project scheduling library // European Journal of Operational Research. – 1996. – Vol. 96. – P. 205–216.</p>
        </note>
      </ref>
      <ref>
        <note>
          <p>9. Singh A. Resource Constrained Multi-Project Scheduling with Priority Rules &amp; Analytic Hierarchy Process // Proc. of 24th DAAAM International Symposium on Intelligent Manufacturing and Automation, 2013, Procedia Engineering. – 2014. – № 69. – Р. 725–734.</p>
        </note>
      </ref>
      <ref>
        <note>
          <p>10. Vanhoucke M. Integrated Project Management Sourcebook: A Technical Guide to Project Scheduling, Risk and Control. Springer. – 2016. – 286 p.</p>
        </note>
      </ref>
    </ref-list>